Construction & Infrastructure Dispute Resolution


Rahman’s Chambers has long experience of assisting both the public sector & private sector entities in the constriction sector in resolving disputes. Our involvement has been found crucial at procurement, awarding, implementation stages. While at the procurement stages, disputes are resolved at the High court or CPTU, at awarding and implementation stages the disputes are mostly resolved by arbitration or mediation.

Mr. Mohammed Forrukh Rahman has been consecutively ranked (Band II) for Corporate & Finance.

– Chambers & Partners, 2021

“described by interviewees as “very caring and friendly to his clients.” Further sources report that “he tries to understand the client’s needs and also offers options.”

– Chambers & Partners, 2020

“he is a knowledgeable and very co-operative person. I have discussed many issues with him and he gives me the right suggestions.”

– Chambers & Partners, 2019

“Their response times are excellent and they make you feel generally very well informed.”

– Chambers and Partners 2018

The ‘very responsible, responsive and knowledgeable’ Mohammed Forrukh Rahman heads the firm.

– Legal 500, 2018

We are recommended for Business law by Asialaw 2021.

Practice Guide – Construction

In recent years there has been an increasing amount of public spending on infrastructure & development projects like building new roads, highways, power plants, bridges & flyovers, land and seaports, rail links, multipurpose overpasses, etc. The said works are carried out by local and international contractors having a high level of expertise in general. Depending on the nature of the project, sector & parties involved, the mode of procurement can be very different. Generally, as per the policy and guidelines of the Public-Private Partnership Authority (PPPA) and other procurement rules & regulations, procurement can be classified as follows: G2G partnership for PPP; PPP projects and Non-PPP projects. Depending on the “principal approval” of ERD, the concurrence of concerned law ministry & ”principal approval” of PPPA a project can be G2G implemented PPP project (solicited/unsolicited) or only PPP project (solicited/unsolicited). The bidding process for the solicited project (whether for PPP or non-PPP) may also vary depending on the approval. Participating in bid complying timetables & also preparing documents as per instruction of tender documents, preparing an unsolicited proposal, etc. is a very challenging work both for national & international bidders. Relevant law comes into play when it comes to bidding/submitting proposal, e.g., Policy for Implementing PPP Projects through Government to Government (G2G) Partnership, 2017, Procurement Guidelines for PPP Projects, 2016, Guidelines for Unsolicited Proposals, 2016, Public Procurement Act 2006, Public Procurement Rules, etc., and hence require legal support. Legal services are often required for the negotiation of contractual terms and also in taking timely steps and filing complain or other lawful recourse while evaluation is taking place in a highly competitive environment.

Our completed works are: 

  • Initiated a construction arbitration proceeding against the land developer for failure to hand over the apartment and pay arrears penalties even after completion of construction.
  • Advised and also appeared as a counsel for a major power sector at different forums including arbitral tribunal, high court & lower court involving failure to ensure dependable & contractual capacity and associated liquidated damages involving a 105 MW diesel-fired plant at Bheramara, Kustia and a 105 MW furnace oil-fired plant at Noapara, Kustia.
  • Resolution of Dispute between Power Division and Harbin Power Engineering Company Limited on 100 MW Simple Cycle Gas Turbine Power Plant involving execution of contract and return of Bank Guarantee.
  • Legal consultant on an international Arbitration between Smith Co Gen. (BD) Ltd vs. BPDB and GOB on the execution of foreign award passed by an arbitral tribunal constituted under ICC rules involving failure to get consent and approval for power project & failure to arrange plant, financial closing, etc.
  • Successfully handled Writ petition 3512/2009- Energy Prima Limited vs. BPDB, relating to a power plant contracted on a rental basis, where complex claims over customs exemption as per Implementation Agreement, rights and liabilities arising out of force majeure, delay, liquidated damages etc. under PPA are litigated.
  • Provided legal assistance by filing an appeal before Central Procurement Technical Unit (CPTU) for Sonali Polaris F.T. Ltd. in a major IT-procurement matter.
  • Rahman’s Chambers successfully completed two local arbitration between landowner and developer and received favorable awards.

Our services include


  • Pre bidding dispute resolution
  • Bidding stage dispute resolution
  • Post bid dispute resolution
  • Writ Petitions & Judicial Review
  • Infrastructure Contractual disputes
  • Construction contract disputes
  • Construction and Infrastructure arbitration
  • Construction and Infrastructure litigation

Our Downloads


Related Resources - Library


The value of law reports in the legal profession cannot be overemphasized. They can be regarded as the life-wire of the legal profession. We have a rich library with a mixture of printed and online legal databases. We have printed version of All England Commercial Cases, Indian Digest of  Supreme Court cases, Yearbook Commercial Arbitration of Wolter Kluwer and most law reports of Bangladesh. We subscribe to the online legal database Manuputra providing access to most reputed law reports. Read more

Translate »